To anchor, the bridge plans the spot and scope, readies the windlass, approaches slowly into wind or tide, lets go almost stopped, and keeps an anchor watch.
Updated 2026-11-09
Answer
To anchor a ship, the bridge team chooses a suitable position, the forecastle party prepares the anchor and windlass, and the ship approaches slowly heading into the wind or tidal stream. The anchor is let go with the ship almost stopped, cable is paid out as she drops back, and once the anchor holds the ship shows anchor signals and keeps an anchor watch.
In detail
Planning starts before arrival. The position needs good holding ground (mud and firm sand hold well, rock and weed poorly), enough water for the draught at low tide, and some shelter from the expected wind and sea. It needs swinging room as well. The ship will swing around the anchor on a circle whose radius is roughly her length plus the length of cable out, and that circle must clear other ships, charted dangers, shallows, pipelines and cables. In port approaches the anchorage is often assigned by the port or VTS. The amount of cable depends on the depth, the holding ground and the weather. Rules of thumb vary between companies, but more cable is used in deeper water, poor holding and bad weather. Cable is counted in shackles of 15 fathoms, about 27.4 metres.
Preparation:
- The engine room is warned and the engines are put on standby.
- The anchor party goes forward in good time, tests the windlass and brake, and removes the lashings and stoppers.
- The anchor is walked out of the hawse pipe until it is clear and ready, then held on the brake.
- Communication between bridge and forecastle is tested by radio, with agreed signals as a backup.
On the approach the ship heads into whichever of wind or stream has more effect on her. A large laden ship needs a long run to lose her speed, so the engine is reduced well before the position. At the moment of letting go she should be almost stopped over the ground, or moving slowly astern.
In shallow water the anchor can be let go from the hawse pipe and controlled with the brake. In deeper water it is usually walked back with the windlass all the way to the seabed first, because an anchor and cable running free can gather more speed than the brake can stop. Cable is then paid out steadily as the ship moves astern, so it lies along the seabed and does not pile on top of the anchor.
The officer forward reports where the cable leads and how much weight it carries. The ship is brought up when the cable rises taut and then dips slack again as she rides to her anchor. The bridge fixes and logs the position, time, depth and cable length. Under Rule 30 of the COLREGs she shows a black ball forward by day and anchor lights at night. Ships of 100 metres and over use their working lights to illuminate the decks as well.
At anchor the officer of the watch checks the position regularly by bearings, radar ranges and GNSS, often with an anchor watch alarm set. Signs of dragging include the position moving outside the swing circle, the ship lying across the wind, and a cable that jerks or changes its lead. The master is called at once. The response may be veering more cable, using the engine to ease the strain, letting go the second anchor, or heaving up and re-anchoring.
Related Terms
Continue Reading
More Questions in Shipboard Operations
An engine-room round compares readings, sounds and smells with normal values for the current load, logs real figures and spots trends before alarms do.
A toolbox talk is a short safety briefing at the job site before work starts, held before higher-risk work and repeated whenever the job or conditions change.
The core precautions before entering an enclosed space — atmosphere testing, permit, ventilation, standby and communications — because these spaces still kill seafarers.
Safe bunkering means an agreed plan and checklist, deck prepared against spills, close watch at topping off, a MARPOL sample and checked delivery figures.